QTS Cambois Data Centre Campus: permitted

Mar 2025 · United Kingdom

// Facts, as published
Facility status
permitted
// Curator note

Up to £10bn (Blackstone/QTS). Outline consent March 2025; phase 1 reserved matters approved; phases B/C applications June 2026; completion estimated 2035.

// Parties
operator
QTS US
// Facilities
subject
QTS Cambois Data Centre Campus Cambois GB
// Evidence
Archived primary
capture #1795 · 22 Oct 2026 · HTTP 200 · sha256 f61b5b27e87eb99b7862f01ecfb81aa181b47342b81f732414fec2517dc34596
// Version history
VersionStatusGradeRightsRecordedReason
v1draftBpending_review22 Oct 2026created